| SL
NO. |
STAGE
OF WORK |
%
OF PAYMENT |
| 1 |
On Allotment |
25% |
| 2 |
On Completion of Foundation |
15% |
| 3 |
On Completion of Basement Roof |
10% |
| 4 |
On Completion of Ground Floor Roof Slab |
10% |
| 5 |
On Completion of First Floor |
10% |
| 6 |
On Completion of Second Floor Roof |
10% |
| 7 |
On Completion of Third Floor Roof |
10% |
| 8 |
On Fixing of Door & Windows Frame |
5% |
| 9 |
On Completion of Internal plastring
and Flooring |
3% + Deposit
$ Misc.cost * |
| 10 |
On Possession or registration whichever
is earlier |
2% |
* |
Percentage
payment includes Basic cost of reserved
parking along with Terrace/Garden, as
applicable. |
| $ |
Deposits will be calculated
as per the prevailing rate demanded by
statuatory bodies at the time of collection. |
| ^ |
Any additional levies
or charges collectable by government will
be charged seperately as applicable. |